Overview:
When updating the Monitoring Event date fields in Vault, an error occurs: Field: Planned Finish Date must be on or after Planned Start Date.
Root Cause:
There is a validation rule in place on the Monitoring Event Milestone that generates an error message. It occurs whenever a user changes the Planned Start Date field to a date that is later than the current Planned Finish Date.
Solution:
There are two ways to prevent this from happening:
- Remove the validation rules
- Add a condition to the validation rule so that this only applies to Milestone Object Types that are not a Monitoring Event
Related Documentation:
- Vault Help Documentation: Vault Help